December 13, 2022

222 Hoddle Construction Update

🏗️ All concrete slabs have been poured up to and including the Level 9 rooftop/

🏗️ Elevators arrive shortly and installation will begin

🏗️ Glazing to begin installation end of January 2023

🏗️ Services installation has begun (meaning Base Building electrical, plumbing, sprinklers and fire services)

🏗️ Main switchboard has been installed

🏗️ Sub-station is being installed