May 30, 2023

Yves Construction Update

The final Bulk Excavation is due for completion by the end of May. This will be an exciting construction milestone for Yves. The Basement Raft completion will shortly follow by the end of June.

Stage 2 Site Accommodation is Complete as well as Stage 2 Dewatering Well Installation. Basement 3 (lower) Retention system is underway this month.