November 14, 2023

Yves Construction Update

🏗️ YVES Construction Update 🏗️

Exciting progress is unfolding at YVES! Here’s the latest update on our construction journey:

🏢 Jumpform now to Level 5: Our team is making remarkable strides as jumpform construction reaches Level 5. We’re reaching new heights every day!

🏗️ Mezzanine Plant Deck Completed: The mezzanine plant deck is poured and ready to support our vision. Additionally, our mezzanine structural walls are now 80% complete.

🚧 Level 2 Formwork Underway: We’re hard at work on Level 2 with formwork currently underway. This marks the final carpark level.

🎄 Christmas Milestone: We’re thrilled to announce that YVES is on track to reach Level 3 by Christmas, making it a holiday season filled with progress and anticipation.